Alongside the Wellhouse project we (mainly Dan!) having been running a project to reorganise our storage. You might have noticed the Marquee has been parked on the village green for the last few months... this is because our builders have been 'reconfiguring' our old storage area called the ... Read more
Floored!
I have learnt far too much about the process of flooring over the last few weeks... simply put we have been delayed due to it taking longer than anyone imagined for our floor to dry out despite the full range of heating, dehumidifiers and fans being applied.... But TODAY was different, today we ... Read more
Doors…
We now have our new door to the Wellhouse installed with a new 'smartlock': The new oak front door looks darker than we had intended but this is due to the 'tratment' required for warranty and we expect this will mellow. We have all our internal doors fitted and they have shiny new ... Read more
Painting…
Painting is almost finished... this is our new look cloakroom... it is missing some minor things, like a sink but they are in plan... And this is the new entrance area, Brad is working on the units to be installed in the cloakroom and the kitchenette: And this is our main room... The only ... Read more
Fitting
We almost have a new front door.... well we have the frame in... and next week we well get the door and add the new smart lock: We have POWER! And now we juggling multiple 'trades'... we have started painting and the heating team are in installing the air source heat pump - And 'most' ... Read more
Plastered and drying out….
Thursday 16th October and our plasterers have completed the internal skim coat.... Now we have to wait for the screed and the plaster to dry.... We have also completed the detail design work on the kitchenette ... and cloakroom sink: Next week is 'second fitting'... electrics, plumbing, skirting ... Read more
Colour
Time to decide on paint colours.... we reviewed a range of palettes with our potential users and settled on a small number to test... many thanks to Jo Kirk who advised us on potential options and combinations and to Jo Curtis who painted our walls with test samples.... we have homed in on Wattle V ... Read more
Underfloor heating
Things are warming up now we have our underfloor heating pipework installed... The pipeworks covers all of the annexe from the entrance area into the cloakroom and main room: This picture from the main room out into the reception area highlights the difference in lighting now we have the ... Read more
Roofmore
Our roof has now been re-felted... and you can now see the raised area where we will install a new skylight for the entrance area: And the pitched roof to the rear has also been refelted along with new ridge tiles... We still have 2 items to finish on the roofing: Guttering Installation of ... Read more
Roofless
Work has now started on insulating our roof, installing a new sky light for the entrance area and re-tiling the front and fixing a leak. OK, nothing to see here... underneath the tarpaulin is new 100mm insulation laid on top of the existing flat roof, awaiting a new felt finish. This picture ... Read more