We are now in week 4 of the 12 week project and the team have made good progress:
Completed most of the the internal plasterboarding and started plastering, we cant finish plastering yet as we still have to replace the windows:

Finished first fit electrics… do you want another photo of wires (and buckets)?

Started the external wall insulation, this is around the back of the hall, where few dare to venture….

Of course no building project is complete without some surprises…. there are 2 rainwater downpipes that go into drain pipes but surprise, surprise the drain pipes don’t go anywhere…